Amen to list...

seems like what we dont have yet.... currently look for a 3 way screw 
terminal... so far i could not find one with excatly same design as the 
current 2 way but with 3 screws



-----Oprindelig meddelelse----- 
From: Damon Hart-Davis
Sent: Sunday, October 20, 2013 8:35 PM
To: Closed list for developer discussions
Cc: Damon Hart-Davis
Subject: Current rough to-do list top

  * BOM and how to deal with LDR, LED, AVR, RFM23, reg (link?)?

  * Batteries vs USB supply count?

  * ENIG finish

  * Preallocation of initial runs to users and DHD R&D bench

  * Run numbers (20 iTEAD/Bo, 30 PMS)?

  * Box OpenSCAD/STL including fudge factors for 'overprint'.

  * AVR/RFM RX code

  * Power-on-self-test code suitable for Bo and PMS to use also.